The US Army Corps of Engineers awarded RLB Contracting a contract to dredge the Houston Ship Channel. RLB entered into a subcontract with Harbor Dredging who, in turn, entered into a sub-subcontract with Diamond Services for the actual dredge work.
Diamond was responsible for “traversing the hopper barges from [the] excavation site to the unloading site.” I have no clue what that means but presumably it is not relevant to this analysis.
More importantly to the quantum meruit issue, Diamond was required to perform all work necessary or incidental to complete its part of the job.
The parties encountered site conditions that were not anticipated where Diamond’s dredge was excavating. The presence of tires in the channel, as well as other issues, slowed the job considerably. After Diamond threatened to abandon the project, RLB petitioned the Corps for an equitable adjustment.
The Corps responded that to consider pricing adjustments RLB would need to release all claims it may have for differing site conditions at the project. In response, RLB withdrew its request to adjust pricing.
Due to Diamond’s obligation to perform all necessary work, Diamond continued its efforts. At project completion, Diamond sent an email to Harbor requesting approximately $2 million. Using this cost submission and similar reports sent by Harbor, RLB amended its bid to include an additional $9 million for excess costs associated with differing site conditions.
After negotiations, the Corps and RLB reached a settlement obligating the Corps to pay an additional $6 million for Diamond’s added work. RLB then issued payment to Diamond for $1 million.
Expecting a $2 million paycheck, Diamond was displeased. So Diamond filed a lawsuit.
The trial court dismissed most of Diamond’s claims, but preserved a claim for equitable adjustment expenses under a theory of quantum meruit. Diamond appealed, giving it the opportunity to litigate its quantum meruit claim.
Initially, the Appellate Court offered that “quantum meruit is an equitable theory which permits a right to recover . . . based upon a promise implied by law to pay for beneficial services rendered and knowingly accepted.” Recovery is limited to situations in which non-payment for the services rendered would result in an unjust enrichment to the party benefited.
However, recovery based on an express contract and on quantum meruit are inconsistent, as the damaged party’s remedies are contained in the contract. This express-contract bar applies not only to the plaintiff seeking quantum meruit recovery from the party with whom it contracted, but also when the plaintiff seeks recovery from third parties who benefitted from plaintiff’s performance.
Because the express contract between Diamond and Harbor covers the damages that Diamond alleges under quantum meruit, Diamond’s quantum meruit claims have no merit.
Despite that, the Appellate Court seemed to be willing to consider Diamond’s claim for expenses related to work performed outside of its contract with Harbor. But since Diamond “failed to present any meaningful evidence on the amount of expenses it incurred for work it performed for which it has not already been paid,” those claims also fail.
Judgment for RLB and Harbor is affirmed; Diamond lost this case because it failed to satisfy an evidentiary burden in the trial court. See Diamond Service Corp v. RLB Contracting; Case No. 23-40137; US Court of Appeals, 5th Circuit; August 16, 2024: https://casetext.com/case/diamond-servs-corp-v-rlb-contracting-inc.
Questions / Issues / Comments:
1. Cases on QM can be confusing. The benchmark seems to be the existence of a contract (or not), and the question of whether or not the contract governs the delivery and pricing for what was furnished. By analogy, if a contract for car repairs includes replacement of the engine but the service shop also replaces the transmission, then presumably the shop has a valid QM claim for the value of the added transmission parts and labor, assuming it was necessary to make the car operable. But no QM claim will exist for engine replacement as the contract will govern that issue, even if the vendor’s expenses far exceed what was anticipated.
2. Damages for QM claims are difficult and subjective. If I did not request delivery of the Wall Street Journal and yet it is delivered to me daily, am I required to pay for it although I never read it? If my neighbor voluntarily mows my gnarly lawn on Saturday without my knowledge, must I pay fair market value for that service although I had planned to do it myself on Sunday?
3. Family Relations. My conclusion is that the theory of unjust enrichment must be the sibling of quantum meruit. Perhaps the theories of quasi-contract, constructive contract, and contract implied by law are first cousins.
Stuart A. Lautin, Esq.** Board Certified, Commercial (1989) and Residential (1988) Real Estate Law, Texas Board of Legal Specialization
Licensed in the States of Texas and New York
Reprinted with the permission of North Texas Commercial Association of REALTORS®, Inc.